Projects & Progress

Following municipal projects from planning through completion.
Initial baseline: October 2026

About These Project Updates

The information below is based on the Village of Harrison Hot Springs' CAO Third Quarter Update, dated October 19, 2026.

Project statuses reflect what Village administration reported at that time. They are not independent confirmation of current completion.

HVF will continue following these projects and update this page as new information becomes available.

Project Directory

Miami River South Bridge — Permitting
Dike Upgrade — Design / Approvals
Splash Pad — Planning
Cedar Avenue Sanitary Project — Design
Hot Springs Source Feasibility Study — Consultant Procurement
Alder Avenue Storm Upgrade — Procurement
SCADA System Upgrade — In Progress
Naismith Avenue Repaving — Contract Awarded
Hot Springs Road Sidewalk / Rain Garden — Contract Awarded
GIS / Asset Management — In Progress

Current Project Updates

Miami River South Bridge

Status reported by Village
October 2026: Engineering design complete; environmental permitting underway.

What we're waiting to confirm: Confirm approvals, budget and construction schedule.

Source: CAO Q3 Update · October 2026


Dike Upgrade

Status reported by Village – October 2026: The 70% design was in progress. A Water Sustainability Act application had been submitted to FrontCounter BC, and authorization from Fisheries and Oceans Canada (DFO) was in progress.

What we're waiting to confirm: Final design, regulatory approvals and project funding.

Source: CAO 2026 Third Quarter Update · October 19, 2026


Splash Pad

Status reported by Village – October 2026: Design concepts and potential locations are under review. A community survey was underway during the reporting period.

What we're waiting to confirm: Publication of the community survey results, confirmation of the preferred location and anticipated project cost.

Source: CAO 2026 Third Quarter Update · October 2026


Cedar Avenue Sanitary Project

Status reported by Village – October 2026: Survey completed and draft engineering design prepared. Landscape design remains pending.

What we're waiting to confirm: Confirm the final design, approved budget and anticipated construction schedule.

Source: CAO Q3 Update · October 2026


Hot Springs Source Feasibility Study

Status reported by Village – October 2026: The request for proposals closed July 2, 2026. Consultant contract and arrangements were reported as being in progress.

What we're waiting to confirm: Consultant appointment, study cost and anticipated completion date.

Source: CAO Q3 Update · October 2026

Alder Avenue Storm Upgrade

Status reported by Village – October 2026: Engineering design completed and procurement initiated.

What we're waiting to confirm: Contract award, approved budget and anticipated construction schedule.

Source: CAO Q3 Update · October 2026

SCADA System Upgrade

Status reported by Village – October 2026: Phases 1 and 2 completed. Phase 3 remains in progress.

What we're waiting to confirm: Final completion date and total project cost.

Source: CAO Q3 Update · October 2026

Naismith Avenue Repaving

Status reported by Village – October 2026: Contract awarded to Grandview Blacktop. Work scheduled to be completed in the fourth quarter of 2026.

What we're waiting to confirm: Actual completion date and final project cost.

Source: CAO 2026 Third Quarter Update · October 19, 2026

Hot Springs Road Sidewalk / Rain Garden

Status reported by Village – October 2026: Contract awarded to Eastvale Contracting, with construction scheduled for the fourth quarter of 2026.

What we're waiting to confirm: Actual construction completion date and final project cost.

Source: CAO Q3 Update · October 2026

GIS / Asset Management

Status reported by Village – October 2026: GIS and asset management updates are ongoing with the Fraser Valley Regional District. Software options are under review.

What we're waiting to confirm: Final implementation plans, software selection and associated costs

Source: CAO Q3 Update · October 2026

Projects Reported as Completed

The following projects were reported as completed in the CAO's 2026 Third Quarter Update:

  • Lillooet Avenue West Streetscape Plan

  • Lift Stations #5 and #6

  • Walnut Avenue Sidewalk Extension / Three-Way Stop Intersection

  • Water and Wastewater Treatment Plant Master Plans

What we're following: Final project costs and any outstanding close-out information where applicable.

Source: CAO 2026 Third Quarter Update · October 2026

Completion statuses reflect the information reported by Village administration.

Source Documents

The information in this report is drawn from official Village of Harrison Hot Springs documents.

October 19, 2026 — Regular Council Agenda Package

Includes the CAO's 2026 Third Quarter Update, which provides the initial project statuses used in this report.

Reporting note: Project statuses reflect information reported by Village administration. This page will be updated as additional Council decisions, project reports and financial information become available.

Last updated: October 23, 2026.